Short answer: From 1 July 2026, Sydney Water charges the full infrastructure contribution for drinking water and wastewater, up from 50% in 2025-26. You pay the number of Equivalent Tenements (ETs) your project adds, multiplied by your Development Servicing Plan price. The amount appears in your Section 73 Notice of Requirements and is paid before the certificate issues.
The last step of a four-year phase-in took effect on 1 July 2026. A contribution capped at a quarter of its full price in 2024-25 is now four times that figure, before indexation. If your feasibility was costed during the discount years, run it again.
This guide uses Sydney Water’s own method and worked examples to show what the full charge means for a dual occupancy, an apartment block, a subdivision and a commercial site.
What are Sydney Water developer charges?
Sydney Water calls them infrastructure contributions. IPART and most developers still say developer charges or DSP charges. They are the same thing: a one-off payment towards the drinking water and wastewater network that new development draws on.
The NSW Government set these charges to zero in 2008. They came back in stages:
| Financial year | Share of the full drinking water and wastewater charge |
| 2023-24 | 0% |
| 2024-25 | 25% |
| 2025-26 | 50% |
| From 1 July 2026 | 100% |
Recycled water and stormwater contributions were never phased in. Where they apply, such as the Rouse Hill and Hoxton Park recycled water areas or the Mamre Road stormwater precinct, they have been charged at full price all along.
Prices sit in Development Servicing Plans (DSPs). A DSP is a pricing document registered with IPART that sets one price for a defined catchment. Sydney Water lists four drinking water DSPs and 14 wastewater DSPs, so every site falls under one of each. That is why two similar projects in different suburbs can receive very different bills.
How does Sydney Water calculate the charge?
The unit of measure is the Equivalent Tenement, or ET. One ET equals the yearly water demand of an average standalone house. Your charge is the ETs your project creates, multiplied by the DSP price, minus a credit for whatever already sits on the site.
For housing, ETs per dwelling fall as density rises, because apartments use less water per home than houses:
| Density (dwellings per hectare) | Drinking water ET per dwelling | Drinking water ET, dual supply area | Wastewater ET per dwelling |
| Under 30 | 1 | 0.67 | 1 |
| 30 to 60 | 0.84 | 0.5 | 0.84 |
| 61 to 100 | 0.71 | 0.5 | 0.71 |
| 101 to 140 | 0.59 | 0.5 | 0.59 |
| Over 140 | 0.56 | 0.5 | 0.56 |
A dual supply area has both drinking water and recycled water pipes, so homes draw less drinking water. Density is measured on developable area, which leaves out roads and public open space. For mixed-use buildings, Sydney Water uses the building footprint instead.
Commercial and industrial projects work differently. Sydney Water converts your forecast average daily flows into ETs, treating 0.43 kL a day of drinking water and 0.38 kL a day of wastewater as one ET. Credits for an existing non-residential building come from its meter records. For bespoke calculations, Sydney Water expects the flows to be prepared by a hydraulic consultant, which is the job of our hydraulic engineers and consultants.
What do real projects pay at full price?
These figures come from Sydney Water’s worked examples for infrastructure contributions, which use a Greater Sydney drinking water price of $3,482.04 per ET and a Malabar wastewater price of $853.80 per ET. The right-hand column is our arithmetic for the same example at last financial year’s 50% cap.
| Sydney Water example | How the ETs are worked out | Full charge (from 1 July 2026) | Same example at the 2025-26 cap |
| Dual occupancy replacing one house, 650 m² lot | 2 dwellings at 0.84 ET, less a 1 ET credit | $2,948.37 | about $1,474 |
| 85 apartments replacing four houses | 85 dwellings at 0.56 ET, less a 4 ET credit | $189,042.62 | about $94,521 |
| 27-lot greenfield stage | 27 lots at 1 ET, less a 1 ET drinking water credit | $113,585.64 | about $56,793 |
| 300-bed hospital on a vacant site | 35 kL/day water, 23 kL/day wastewater | $335,099.23 | about $167,550 |
| 56 apartments over a supermarket, replacing an office | Density method for the homes, flows for the retail, less metered credit | $294,234.09 | about $147,117 |
At those prices, a standalone lot charged one full ET for each service costs $4,335.84. An apartment in a tower above 140 dwellings per hectare costs $2,428.07 before credits.
Your own numbers will differ. Prices vary by DSP area and rise with CPI every 1 July. The DSP price map on Sydney Water’s land development page shows 2026-27 figures. Use the table to judge scale, not as a quote.
Can a bigger lot attract a bigger charge?
Yes, and it catches people out. Sydney Water’s dual occupancy example puts two dwellings on 650 m² in place of one house. At about 31 dwellings per hectare it sits in the 30 to 60 band, so each dwelling counts as 0.84 ET and the charge is $2,948.37.
Put the same project on a 700 m² lot and density drops to about 29 per hectare. Each dwelling is now a full ET. On Sydney Water’s method and example prices, the charge rises to $4,335.84, roughly 47% more. For a two-dwelling project, the cut-off is a lot of about 667 m².
Subdivisions sit on the same edge. Sydney Water’s 27-lot greenfield example works out at 29 lots per developable hectare, one step below the 30 threshold. How your surveyor and civil engineering consultants define developable area on the plan can move a stage between bands. We wouldn’t redesign a subdivision purely to shift a band. You should still know which side of the line you are on before you commit to a land price.
When do you pay, and at which year’s price?
The charge appears in the Notice of Requirements, the letter listing everything you must do before Sydney Water will issue your Section 73 Compliance Certificate. For applications lodged by a water servicing coordinator, Sydney Water says it will send that letter within 60 days. You pay before the certificate issues. Councils generally won’t issue occupation certificates for new properties without one.
Two timing details matter more now that charges are at the full rate:
- Indexation. Sydney Water says you are responsible for the contribution current at the time you are ready to connect. If connection slips past 1 July, budget for the CPI rise.
- Expiry. A Notice of Requirements is valid for 12 months. After that you reapply and pay the application fees again.
The contribution is separate from the cost of building pipes. If a main has to be extended or upgraded, the developer generally pays the full cost, though Sydney Water sometimes contributes under its growth funding policy. Coordinator fees, peg-outs (service protection reports that locate Sydney Water pipes on your site) and pressure and flow statements are on top. Our guide to when you need a Section 73 certificate covers the wider process.
How to check your number before Sydney Water does
- Find both DSP areas for your site on Sydney Water’s map, and check whether it is a dual supply or recycled water area.
- Confirm the developable area figure on your site or subdivision plan, with roads and public open space excluded.
- Work out your density band. Near 30, 60, 100 or 140 dwellings per hectare, calculate both bands.
- List every existing dwelling or connection that should earn a credit. For commercial sites, collect the meter records.
- For non-residential or mixed-use projects, get average daily flow forecasts prepared before lodgement.
- Check the Notice of Requirements date against your construction program and the 12-month expiry.
- Add CPI if connection falls after the next 1 July.
- Budget separately for pipe works, coordinator fees and any asset protection required under Sydney Water building plan referrals.
Our practical guide to Sydney Water requirements for new developments lists the drawings to have ready.
Will IPART’s review change the charges?
IPART’s review of developer charges for metropolitan water businesses opened in May 2026. It covers the method behind charges for Sydney Water, Hunter Water and Central Coast Council, and brings recycled water into the same review, with high-demand users such as data centres in view. IPART plans a draft report in April 2027 and a final report in August 2027.
Our view: don’t bank on a cut. The review is about method, and any new framework is at least a year away. Hunter Water also moved to 100% on 1 July 2026, so this is not a Sydney Water quirk. Budget at the full rate plus CPI, and treat any reduction as a bonus.
When a water servicing coordinator isn’t the right choice
You don’t always need one.
- Complying granny flats. A secondary dwelling approved as complying development under the Housing SEPP doesn’t need a Section 73 certificate. It still needs building plan approval through Sydney Water Tap in.
- Small projects with minor works. If services are available and you only need minor works, such as a new sewer junction or a sewer extension under 25 metres, Sydney Water Developer Direct can handle the application for a fixed cost. For a simple dual occupancy, that can be the cheaper route.
- Hunter Water sites. Hunter Water issues a Section 50 certificate rather than a Section 73, under its own process. Our Hunter Water accredited designers handle that work.
A coordinator earns the fee on major works: unit blocks over four storeys, Torrens title subdivisions of five lots or more, jobs that move Sydney Water pipes, and commercial or mixed-use sites where flows drive the charge. No coordinator can negotiate the DSP price itself. What a coordinator can do is make sure the density, credits and flows Sydney Water uses are right, and that anything built near a pipe respects the rules for building over or near a Sydney Water sewer.
FAQ
Did Sydney Water developer charges go up on 1 July 2026?
Yes. Drinking water and wastewater contributions moved from 50% of the IPART-registered price to 100%, and prices were also indexed by CPI. Recycled water and stormwater contributions were already at full price.
Can I lock in a lower price by applying early?
Sydney Water says you are responsible for the contribution current when you are ready to connect, and a Notice of Requirements lapses after 12 months. Applying early helps your program, but don’t rely on it to fix the price.
Do granny flats pay Sydney Water infrastructure contributions?
A granny flat approved as complying development under the Housing SEPP doesn’t need a Section 73 certificate, which is the process contributions are charged through. Building plan approval is still required.
Who works out the charge?
Sydney Water confirms which DSP areas apply during the Section 73 application and sets the amount in your Notice of Requirements. Your water servicing coordinator lodges the application and can check the inputs before it goes in.
Is the contribution the same as the coordinator’s fee or the cost of new pipes?
No. The contribution goes to Sydney Water for network capacity. Coordinator fees are charged at market rates, and main extensions or protection works are priced separately as construction.
Will the IPART review lower charges?
Nobody can say yet. IPART plans to publish draft decisions in April 2027 and a final report in August 2027, so budget on current DSP prices until then.
Get your Section 73 contribution checked
LP Consulting Australia is a Sydney Water accredited Water Servicing Coordinator at Suite 601, Level 6, 262 Pitt Street, Sydney, working across Sydney, the Blue Mountains and the Illawarra. Principal Engineer Louis Panagopoulos, a Fellow of Engineers Australia, has practised as a civil engineer in Sydney for more than 36 years, and the firm holds ISO 9001, ISO 14001 and ISO 45001 accreditation.
We prepare Section 73 applications, flow and pressure statements and water and sewer main designs, then manage the Notice of Requirements works through to Work As Executed drawings and certification. That includes the Sydney Water water and sewer design for a 49-home subdivision in Kellyville.
Send your DA Notice of Determination, architectural drawings and survey plan through our contact page, or call (02) 9223 4444.